A RERA order is not the same thing as a solution. A buyer can win a refund order and still wait years for the money if the developer has none. A developer can win on some points and still face appeals, recovery proceedings and penalties. In many NCR disputes, both sides would be better off with a deal: one that gets the buyer a home or money on a timetable the developer can actually meet, and that lets the developer put its resources into finishing the project rather than fighting about it.
Settlement doesn't suit every case. Some developers make offers they have no intention of honouring. Some buyers need an order because there is no trust left. But where both sides want a result, a well-structured settlement is often the fastest and most reliable route. This page explains how settlements and mediation work in real estate disputes, what usually goes into them, and how to make sure the deal holds.
The legal framework
The Real Estate (Regulation and Development) Act, 2016 doesn't have a detailed mediation procedure, but it encourages settlement. Section 32(g) lists among the authority's functions taking measures to facilitate amicable conciliation of disputes between promoters and allottees through dispute settlement forums set up by consumer or promoter associations.
Several authorities have acted on this. MahaRERA in Maharashtra set up a conciliation forum some years ago, and other authorities, including UP RERA, have set up conciliation mechanisms of their own, with the details and level of activity varying over time. Even where there's no formal forum, authorities routinely allow complaints to be adjourned for the parties to talk, and record settlements when they are reached.
Outside RERA, there are other routes:
- the Mediation Act, 2023, which provides a general framework for mediation, including pre-litigation mediation, with settlement agreements that are enforceable like court judgments (subject to the provisions that have been brought into force);
- mediation cells attached to consumer commissions under the Consumer Protection Act, 2019, for disputes before those commissions;
- court-annexed mediation centres, where a matter is pending before a court; and
- Lok Adalats, which settle certain disputes by consent, with awards treated as decrees.
And of course parties can simply negotiate directly, with or without lawyers, and record what they agree.
When settlement makes sense
For a buyer, settlement is worth considering where:
- you want the flat, the project is genuinely moving, and a firm possession date with some compensation is better than years of litigation;
- you want your money back, and the developer can pay over a period, but an order for the full amount at once would just push it into default;
- the developer is offering something useful that an order couldn't give you, such as a ready unit in another tower or project; or
- you need certainty for a home loan, a move or a family decision.
For a developer, settlement makes sense where:
- liability for delay is clear and the main argument is about amount;
- an order would require a pre-deposit to appeal that the developer can't afford to tie up;
- a large number of buyers have similar claims, and a group solution is more manageable than hundreds of orders; or
- the developer needs buyers' cooperation, for instance to complete the project, obtain consents or raise finance.
Settlement is less suitable where one side is acting in bad faith, where there's a history of broken promises, or where the developer is in serious financial trouble and any money it pays one buyer may be challenged later (for instance in insolvency).
What settlements usually contain
For buyers who want the flat
- a firm possession date, after the occupancy certificate, with a clear consequence if it's missed, such as resumption of the right to a refund with full interest;
- delay compensation for the period of delay so far, as a lump sum, a credit against remaining dues, or both;
- continuing compensation for each month beyond the new date;
- a freeze or waiver of disputed charges, such as escalation, increases in super area, preferential location charges, interest the developer claims on the buyer's late payments, or holding charges;
- a revised payment schedule for remaining instalments, linked to actual progress; and
- specific commitments on amenities, specifications or defects, where those were in dispute.
For buyers who want to leave
- the principal amount to be refunded;
- interest, in full or part, and the period it covers;
- a payment schedule, with fixed dates, preferably secured in some way, such as post-dated cheques, a bank guarantee or a charge over unsold inventory;
- what happens if a payment is missed: typically, the whole balance becoming due immediately, interest at the prescribed rate on the unpaid amount, and the buyer's right to revive the complaint or seek an order in the agreed terms;
- arrangements with the home loan bank, where there's a loan; and
- cancellation of the allotment and return of original documents once payment is complete.
Alternate units
Developers with several projects sometimes offer a unit in a completed or nearly completed project in place of the delayed one. These offers can be attractive, but buyers should compare carefully: location, carpet area (not just super area), specifications, the occupancy certificate status of the alternate project, maintenance charges, and whether the price difference is fair. The alternate unit should come with a fresh, properly registered agreement, and the transfer of payments from the old unit to the new one should be clearly documented.
Making the settlement stick
The biggest risk in a settlement is that one side doesn't do what it promised, usually the developer failing to pay or deliver on time. A buyer who has withdrawn a complaint on the strength of a promise that then isn't kept is worse off than before. The structure of the settlement should protect against that.
Record it before the authority
Where a complaint is pending, the settlement should be filed before the authority and the complaint disposed of in terms of the settlement, so that the settlement becomes part of an order. That way, if the developer defaults, the buyer can enforce the order through recovery under Section 40 and seek penalties under Section 63, rather than having to start a fresh case on a private agreement. Simply withdrawing a complaint after signing a private agreement is riskier.
Include a default clause
The settlement should say exactly what happens if a payment or a possession date is missed. Common terms are that the buyer's original claim revives in full, credit is given only for amounts actually received, and interest runs on the unpaid balance at the prescribed rate from the original due date.
Be precise
Dates, amounts, unit numbers, carpet areas, the account into which payments will be made, the documents to be exchanged, and who pays stamp duty and registration charges. Vague settlements produce new disputes.
Security
Where money is to be paid over time, some security helps: post-dated cheques (which bring the remedy under Section 138 of the Negotiable Instruments Act, 1881 if they bounce), a bank guarantee, an escrow, or an earmarked unsold unit. Not every developer can provide strong security, but the question should always be asked.
Releases
Developers will want a release of claims in return for what they give. That's fair, but the release should be limited to the claims actually being settled, and should take effect only when the settlement has been performed, not when it is signed. A buyer shouldn't give up the right to claim for structural defects that haven't yet appeared, for instance, in a settlement about delay.
Home loans and settlements
Where the buyer took a home loan, the bank is usually a party to the tripartite agreement and has a charge over the buyer's rights in the unit. That affects settlements in two ways.
- Refunds: the bank will generally want the outstanding loan repaid out of the refund before anything is paid to the buyer. Settlements should provide for payment to the bank first, with a no-dues letter, and the balance to the buyer.
- Revised payment plans: changes to the schedule of disbursements need the bank's agreement.
Where the developer was paying pre-EMI interest under a subvention scheme and stopped, the settlement should address who pays what to the bank, and how the buyer's credit record will be protected. See our page on subvention scheme disputes.
Tax points
Interest or compensation received by a buyer under a settlement may have tax consequences, and developers sometimes deduct tax at source from interest payments. The treatment depends on the nature of the payment and the buyer's circumstances. Both sides should take advice from a chartered accountant on how the settlement amounts will be treated before signing, so that there's no surprise about the net amount received.
Group settlements
In large delayed projects, developers increasingly negotiate settlements with groups of buyers or with the association of allottees, rather than one buyer at a time. A group settlement typically sets out a project-wide plan: a revised completion schedule, a standard formula for delay compensation, how remaining dues will be handled, and options for buyers who want to leave. Individual buyers then opt in.
Group settlements can work well. They give the developer certainty and the buyers negotiating strength. But individual buyers should still check how the formula applies to them, especially if their payment history or agreement terms differ from the typical case, and shouldn't feel pressured to sign if the terms don't suit them. See our page on group complaints.
How a mediation actually runs
Where a mediator or conciliator is involved, the process usually looks like this:
- Agreement to mediate. Both sides agree to try mediation, and the authority, commission or court adjourns the case if one is pending.
- Exchange of positions. Each side sets out what it wants and why, often in a short note with key documents: the agreement, the payment ledger, the project's status.
- Joint session. The mediator meets both sides together to understand the dispute and the main issues.
- Private sessions. The mediator meets each side separately, in confidence, to explore what each could accept. This is where most progress is made.
- Proposals and counter-proposals, often over several sessions.
- Settlement agreement, if a deal is reached, signed by both sides and filed where the case is pending.
Mediation is confidential. What is said in it can't generally be used later in the case if the mediation fails. That allows both sides to be more open than they would in a hearing.
The mediator doesn't decide anything. If no settlement is reached, the case goes back to the authority or court, and nothing is lost except time.
Negotiating well
For buyers
- Know your claim. Work out what an order would likely give you: the refund or interest at the prescribed rate, for the right period, on the right amounts. That's your benchmark.
- Know the developer's position. Check the project's RERA page, quarterly updates, audit reports and the number of orders against the developer. A developer with many unpaid orders may not be able to pay an order quickly, which affects what a realistic settlement looks like.
- Value certainty. A smaller sum that will actually be paid may be worth more than a larger order that won't. But don't accept less than your claim is worth just because the developer says it has no money; ask for evidence.
- Get advice on the documents. Developers' standard settlement forms are often drafted to favour the developer, particularly on releases and default clauses.
For developers
- Make offers you can keep. A settlement you then breach is worse than an order: it destroys trust with the buyer and the authority, and the buyer usually gets the full claim back plus interest.
- Be consistent. Buyers in the same project talk to each other. Very different terms for similar buyers cause resentment and more complaints.
- Explain the numbers. Buyers are more likely to accept an offer when they understand how it was calculated and what the alternative is.
- Don't use possession as leverage. Making possession conditional on signing a waiver of all claims is a common practice that authorities view poorly, and such waivers are often given little weight later.
An illustration
Here's a made-up example. A buyer in a Noida project paid Rs 70 lakh for a flat due in 2020. The tower is now at the finishing stage, and the developer expects the occupancy certificate within eight months. The buyer has filed a complaint for refund with interest, mainly out of frustration, though she would still like the flat if she could trust the new date.
At the first hearing, the authority suggests the parties talk. After two meetings, they agree:
- the buyer will keep the flat;
- the developer will pay delay interest at the prescribed rate up to the date of settlement, by adjusting it against the final instalment due at possession, and paying any excess in cash at possession;
- the developer will obtain the occupancy certificate and offer possession by a fixed date, ten months away;
- if it doesn't, it will pay interest at the prescribed rate for each further month, and the buyer may at any time after a further three months choose a refund with interest from the original payment dates;
- escalation charges and a disputed increase in super area are waived; and
- the settlement is filed before the authority and the complaint disposed of in its terms.
The buyer gets the flat, a clear date and real protection if it's missed. The developer avoids a refund order on a unit it can deliver, and keeps the buyer's remaining payment for the project.
How we help
We act for buyers and for developers in negotiations and mediations, though never for both sides in the same matter. For buyers, we work out what the claim is worth, review offers and settlement documents, negotiate, and make sure the settlement is recorded in a way that can be enforced. For developers, we help design settlement offers and group schemes that are fair and affordable, prepare documentation, and record settlements before the authority.
Where settlement isn't possible, we continue with the complaint or defence. Trying to settle doesn't weaken anyone's position in the case.
Settling at different stages
A dispute can be settled at any point, but what a good settlement looks like changes as the case moves on.
Before any complaint
A buyer who has sent a legal notice, or a group that has written to the developer, may get a response offering talks. At this stage nothing has been decided, so both sides are negotiating on their view of the likely outcome. The advantage is speed and cost. The risk for the buyer is that a private agreement, not recorded in any order, is harder to enforce. Where the deal involves payments over time, it may be worth filing a complaint anyway and recording the settlement in it. See our page on legal notices to builders.
While the complaint is pending
This is the most common stage. Each side has seen the other's pleadings, and the authority may have given an indication of its view at a hearing. Settlements here are usually recorded before the authority, which is the safest way to do it.
After the order
Once the authority has passed an order, the buyer has a clear entitlement. A settlement at this stage is usually about how and when the order will be paid, and sometimes a modest reduction in exchange for speed or certainty. If the developer has appealed, it will have had to make a pre-deposit under Section 43(5); a settlement can provide for release of that deposit to the buyer, with the appeal withdrawn. That's often an efficient outcome.
In recovery
Where a recovery certificate has been issued and the district administration is pursuing the developer, settlements often provide for a payment schedule in exchange for the recovery being put on hold, with the right to resume it immediately on default. See our page on recovery certificates.
In insolvency
Once a developer is admitted into insolvency, a moratorium under Section 14 of the Insolvency and Bankruptcy Code, 2016 stops proceedings against it, and individual settlements are generally not possible. Buyers' claims are dealt with through the insolvency process. Payments made to individual buyers shortly before insolvency may also be examined by the resolution professional. See our page on builder insolvency.
Common mistakes
- Withdrawing the complaint before the money arrives. Keep the complaint alive, or record the settlement in it, until performance.
- Signing the developer's form without reading it. Standard forms often contain wide releases and weak default clauses.
- Agreeing a lump sum without checking the calculation. Work out what interest at the prescribed rate would be before agreeing to less.
- Ignoring the bank. Refund settlements that don't deal with the home loan create new problems.
- Accepting vague possession promises. "Possession shortly" isn't a date. Neither is "subject to the occupancy certificate" without a long-stop date and a consequence.
- For developers, over-promising. Every broken settlement makes the next negotiation harder, with that buyer and with every other buyer in the project.
Frequently asked questions
Can a RERA complaint be settled?
Yes. Parties can settle at any stage, and the authority will usually dispose of the complaint in terms of the settlement when it's filed before it.
Does RERA have a mediation process?
Section 32(g) asks authorities to facilitate amicable conciliation, and some authorities have set up conciliation forums. Authorities also routinely give parties time to settle. Mediation under the Mediation Act, 2023 and through consumer commissions is also available.
What if the builder breaks the settlement?
If the settlement was recorded in an order, it can be enforced through recovery and penalty proceedings. A good settlement also revives the original claim on default.
Should I accept an alternate unit?
Possibly, after comparing location, carpet area, specifications, occupancy certificate status and price, and with a fresh registered agreement that transfers your payments clearly.
Can the builder insist on a waiver of claims before giving possession?
Builders often ask, but authorities view such conditions poorly, and waivers signed under pressure to obtain possession are often given little weight later.
What happens to my home loan in a refund settlement?
The bank usually has to be repaid first from the refund, with a no-dues letter issued, and the balance paid to you.
Is what is said in mediation confidential?
Yes, generally. Statements made in mediation can't usually be used in the case if mediation fails.
General information about settlement, conciliation and mediation in disputes under the Real Estate (Regulation and Development) Act, 2016. Each settlement depends on the parties' circumstances, and state authorities' conciliation arrangements differ and change. Tax treatment of settlement amounts should be checked with a chartered accountant. Not legal advice.
Are you having a legal problem in Settlement & Mediation Between Buyer and Builder? You don't have to deal with it alone. Let's discuss your situation and explore the appropriate approach to handle it.
There is no pressure or difficult legal language, only clear information based on the circumstances of your Settlement & Mediation Between Buyer and Builder matter.